5 Steps to Prepare for Your Plastic Recycling Equipment FAT

A Factory Acceptance Test (FAT) is a hands-on review of your plastic recycling equipment before it leaves the manufacturer. Your team can watch the equipment run, check that it meets the agreed specifications, and identify any issues while the manufacturer still has the equipment on site. Finding and correcting problems at this stage can help prevent delays and unexpected work once the system arrives at your facility.

Different plastic recycling machine manufacturers may handle FATs differently, so make sure you understand what the test will cover before you arrive. The five steps below cover what to work out beforehand and what to check before you approve the equipment for shipment.

Step 1: Define the FAT Acceptance Criteria

Before the FAT, you and the manufacturer need to agree on what the equipment has to do to pass. Put those requirements in the FAT protocol so you are both working from the same criteria on test day.

A throughput target also needs some context. Saying the machine should process “5 tons per hour” isn’t enough if you don’t define what you’re feeding it. Plastic film, for example, behaves very differently from rigid HDPE. The size and condition of the material, including moisture and contamination, can also change how much the machine processes in an hour.

Be clear about the feedstock you will use, the throughput you expect, the required output size, and how the test will be run. Do the same for the controls and safety functions you want to check, including alarms, interlocks, and emergency stops.

You may need to test some things again once the equipment is installed and connected to the rest of your line. Decide what belongs in the FAT and what will wait for site testing, then get the protocol approved before the FAT date.

Step 2: Check the Equipment Against What You Ordered

Before you run any plastic through the equipment, compare it with the approved drawings, your purchase order, and provided specifications. Check the model and nameplate information to confirm the manufacturer built what you ordered.

Pay particular attention to the major components. Confirm the motors and gearboxes, along with the cutter setup and screen size on the shredder or granulator. Check the electrical and control components against the drawings, and make sure the guards, sensors, door switches, and emergency stops are in place too.

You can also ask the manufacturer to finish their own checks before your team arrives and tell you about any unfinished work or known problems. This way, you won’t have to spend the FAT waiting for basic assembly or wiring work to be finished.

Step 3: Agree on the Test Material and Who Needs to Attend

Decide who needs to attend the FAT and who has authority to approve the results. Your team might include engineering, operations, or project management, along with a third-party inspector if the project requires one. Make sure someone there can make the final call if a problem needs to be fixed before shipment or can wait until commissioning.

Agree on what plastic you will use for the test too. Whenever possible, use material that represents what you actually process. Clean, uniform plastic may run perfectly well but tell you very little if your normal feedstock contains labels, dirt, moisture, or a mix of shapes and sizes.

Confirm who will provide the material and how much you need for the test. If you’re sending your own feedstock, arrange delivery early enough to have it at the manufacturer’s facility before the FAT. Confirm the utilities, PPE, special tooling, and test schedule before your team travels as well.

Step 4: Run the FAT and Record the Results

Now run the equipment with the plastic you agreed on earlier. See whether it hits the throughput and output-size targets in the FAT protocol. If the test calls for readings such as motor load, bearing temperature, or vibration, record them while the equipment is running.

Keep an eye on the controls during the test. Try the Human-Machine Interface (HMI), alarms, interlocks, and emergency stops. If the shredder has overload detection or automatic reverse, ask the manufacturer to demonstrate how those functions work. Use an approved test method rather than creating a jam that could damage the machine.

Record the results as you go. If the equipment misses a target or something doesn’t work as expected, note what happened and what the readings showed at the time. Take photos or video if they will help document the problem.

Step 5: Close Out the Punch List Before You Sign

You may find a few things during the FAT that still need work. Add each one to the punch list and agree with the manufacturer on what happens next. Some may need to be fixed and retested before shipment, while others can wait until installation or commissioning at your facility.

Be specific about what you found. Instead of writing “conveyor speed problem,” record what the conveyor did, what it was supposed to do, and the readings from the test. Assign someone to fix the issue and note whether you need to see it retested before you accept the equipment.

Review the final FAT report before signing. Make sure it includes the test results, the problems you found, and what will happen with each punch-list item. If something will be fixed or tested at your facility, state that clearly in the report rather than treating it as closed.

From FAT to Final Installation

A successful FAT confirms that the equipment met the test criteria you established before shipment. Once the equipment reaches your facility, you still need to verify that it performs as expected after installation and integration with the rest of your processing line.

Installation, commissioning, and operator training can help your team transition from factory testing to full production. Taking the time to verify the equipment under actual site conditions gives you a clearer picture of how the complete system performs and helps address any issues before you move into regular operation.

Video

5 Steps to Prepare for Your Plastic Recycling Equipment FAT

Infographic

5 Steps for FAT Preparation for Plastic Recycling Equipment Infographic

Most innovative solution in tire recycling!

EcoGreen just shred it

Search Blog