Better RDF Starts with Secondary Shredding and Screening

How small should you shred your waste fuel? That depends on who is buying it and how they plan to use it. A cement kiln main burner may require much smaller pieces than a calciner or boiler. Shredding everything finer than the customer requires adds more work without necessarily improving the finished fuel.

Primary shredding breaks down incoming waste into a manageable size, while a secondary RDF shredder brings that material closer to the particle size the end user requires. Screening then separates oversized pieces so you can send them back through rather than allowing them into the finished fuel.

The key is to match each stage of processing to the size and consistency your customer needs so primary shredding, secondary shredding, and screening work together to help you avoid unnecessary processing.

Why Prioritize Particle Size in RDF Production

Your customer will usually specify how small RDF fuel particles need to be because particle size affects how reliably the fuel moves through the customer’s handling and feeding equipment and how consistently it burns. If the finished RDF contains too many oversized pieces, it may cause problems with conveying, feeding, and combustion. Pieces that are too large may clog equipment or fail to feed consistently, while excessive fines can create their own handling and dust concerns.

Smaller pieces can burn more quickly while larger pieces take longer to ignite and burn through. That variation can create uneven combustion and make it harder to maintain stable conditions in the combustion system.

The goal isn’t to make RDF as small as possible. It’s to produce a consistent particle size that matches the customer’s equipment and fuel specifications. Once you know that target, you can determine how much size reduction your process actually needs and avoid spending time and energy shredding material finer than necessary.

What a Secondary Shredder Does to the Material

The mixed waste you shred rarely reaches that target in a single pass because the incoming material can vary so much in size, shape, and composition. After a pass through the primary shredder, the secondary shredder reduces the remaining combustible material to the size the customer requires. The target depends on where the fuel is going. One plant may accept relatively coarse material. Another may require much smaller pieces.

A secondary shredder controls the output through its rotor, cutter setup, and screen basket. Material that fits through the screen leaves the cutting chamber. Larger pieces stay inside and pass through the cutters again.

You can swap the screen to produce a finer or coarser fuel. Keep in mind that the screen opening does not set the exact dimensions of every piece coming out. A long strip of plastic film or textile can turn sideways and pass through even when its length exceeds the size of the opening.

How Screening Completes the Refining Process

Even after shredding, you may still have oversized pieces and unwanted material mixed into the fuel. Removing metals, glass, stones, and other unwanted material may require other equipment. The equipment you need depends on what is coming into the line:

  • Screens: Separate material by size. Oversized pieces can go back through the shredder for another pass. Fines can also be removed if they fall outside the fuel specification.
  • Magnets: Capture magnetic metals from the material stream, including iron and steel.
  • Eddy-current Separators: Deflect conductive metals that aren’t magnetic, including aluminum.
  • Air or Ballistic Separators: Separate lighter combustible material from heavier materials such as stones, glass, and other inerts.

You may not need every one of these stages. The setup depends on what is in your incoming waste and what your customer allows in the finished fuel.

However, removing these materials can improve the fuel in different ways. Glass and stone add weight and increase the amount of ash left after combustion. Wet organic material adds moisture and can lower the fuel’s energy value. Metals are a different problem because they can damage equipment further down the line.

How Better Sizing Protects Downstream Equipment

Getting the material down to the right size and removing unwanted material also protects the equipment that comes after the shredding and separation stages.

Long pieces of plastic film or textiles can wrap around conveyor rollers and screw feeders. Oversized material can bridge across hopper openings and stop fuel from dropping into the feeder. In pneumatic feed lines, heavy pieces can fall out of the air stream and eventually block the pipe.

Metal, stone, and other heavy contaminants create a different problem. They can increase wear on conveyor belts, screw feeders, and other components that move and meter the finished fuel.

Removing oversized pieces and heavy contaminants before they reach this equipment may lead to fewer blockages to clear and less unnecessary wear on moving parts.

Build the Line Around the Fuel You Need to Produce

The most useful question isn’t simply which shredder can make the smallest pieces. It’s whether the entire processing line can consistently produce the fuel your customer wants. Start with the customer’s specifications, then work backward through the material characteristics and acceptable contaminants to determine where each stage of processing earns its place.

That approach can also help you design your process and identify where to spend your equipment budget. Looking at the line as a complete process can help you choose equipment that supports the finished fuel you need rather than paying for processing capacity or features you won’t actually use.

Most innovative solution in tire recycling!

EcoGreen just shred it

Search Blog